Kitchen Remodel Scope of Work Template

Download a free kitchen remodel scope of work template. Covers demo, cabinets, countertops, flooring, plumbing, electrical, and finishing for kitchen contractors.

Download Free Template

Kitchen Remodel Scope of Work Template
Download:

What's Included

Kitchen remodels involve the most trades of any project — demo, plumbing, electrical, cabinets, countertops, flooring, tile, paint, and appliances all need to be coordinated. A scope of work keeps everyone aligned on the sequence and what's included. This template covers the full kitchen remodel from demo to final punch. It's written for contractors and homeowners who want a clear plan. Adjust it for your specific kitchen project.

Project Overview

This scope covers a kitchen remodel including demolition, rough-in trades, cabinetry, countertops, flooring, backsplash, appliances, and finish work.

Typical Projects Include:

  • Full kitchen gut and remodel
  • Cabinet and countertop replacement
  • Kitchen layout change
  • Kitchen refresh (paint, hardware, backsplash)
  • Galley kitchen conversion
  • Open concept kitchen renovation

Scope of Work

Demo & Rough-In

TaskDescription
Kitchen DemoRemove existing cabinets, countertops, backsplash, flooring, and fixtures. Protect adjacent areas.
Plumbing Rough-InMove or add water, drain, and gas lines for the new kitchen layout.
Electrical Rough-InAdd circuits, move outlets, and install lighting boxes per the new plan. Bring kitchen up to code.
Framing & DrywallMove or add walls as needed. Patch and finish drywall after rough-in inspections pass.

Cabinets & Surfaces

TaskDescription
Cabinet InstallationInstall wall and base cabinets per the layout. Level, plumb, and secure to studs.
Countertop Template & InstallTemplate countertops after cabinets. Fabricate and install countertops with sink and cooktop cutouts.
BacksplashInstall tile or other backsplash material. Grout and seal.
FlooringInstall new kitchen flooring — tile, LVP, hardwood, or other material.

Finish & Closeout

TaskDescription
Plumbing FinishInstall sink, faucet, garbage disposal, dishwasher connection, and ice maker line.
Electrical FinishInstall outlets, switches, under-cabinet lighting, and pendant fixtures.
Appliance InstallationDeliver and install all kitchen appliances. Connect and test.
Punch & WalkthroughTouch up paint, adjust hardware, and walk the finished kitchen with the homeowner.

Timeline & Milestones

A full kitchen remodel typically takes 6-12 weeks. The sequence of trades is critical.

PhaseDurationDescription
Demo & Rough-In2-3 weeksDemo, plumbing, electrical, framing, and drywall.
Cabinets & Surfaces3-5 weeksCabinets, countertop template/install, backsplash, and flooring.
Finish & Closeout1-2 weeksFixtures, appliances, paint, and punch list.

Roles & Responsibilities

Homeowner

  • Make all selections on time (cabinets, counters, tile, fixtures, appliances)
  • Provide access and plan for a temporary kitchen
  • Make decisions promptly to avoid delays
  • Process payments per the agreed schedule

Contractor

  • Manage the project schedule and trade sequence
  • Pull permits and coordinate inspections
  • Install or coordinate all work per the plan
  • Maintain a clean and safe work area
  • Walk the homeowner through completion

Materials & Equipment

Cabinets & Counters

  • Kitchen cabinets (wall and base)
  • Countertop material (granite, quartz, etc.)
  • Cabinet hardware
  • Under-cabinet lighting

Surfaces

  • Backsplash tile and grout
  • Flooring material
  • Paint and primer
  • Trim and molding

Fixtures & Appliances

  • Kitchen sink and faucet
  • Garbage disposal
  • Range, refrigerator, dishwasher
  • Range hood or microwave

Quality Control Standards

Cabinet Alignment

All cabinets level, plumb, and aligned. Doors and drawers operate smoothly.

Countertop Fit

Countertops fit properly with clean seams, correct overhang, and accurate cutouts.

Code Compliance

Plumbing, electrical, and framing meet current building code. Inspections passed.

Safety Protocols

Dust Control

Seal off the kitchen from living areas during demo and construction. Use dust barriers.

Utility Safety

Turn off water, gas, and electrical before disconnecting any kitchen systems.

Lead & Asbestos

Test for lead and asbestos in older homes before demolition begins.

Project Documentation

  • Signed contract and scope of work
  • Kitchen design and layout
  • Selection schedule (cabinets, counters, tile, fixtures)
  • Permit and inspection records
  • Change order log
  • Warranty information for all products

Financial Terms

Payment Structure

Kitchen remodels use milestone payments tied to project phases.

Terms & Conditions

  • Deposit due at contract signing (typically 10-20%)
  • Payment at demo completion
  • Payment at cabinet installation
  • Payment at countertop installation
  • Final payment after punch list completion
  • Change orders require written approval before work proceeds

Acceptance Criteria & Sign-Off

The project is considered complete when the following criteria are met:

  • 1All cabinets installed per layout and operating smoothly
  • 2Countertops installed with clean seams and proper fit
  • 3Backsplash and flooring installed per specification
  • 4All plumbing and electrical working and inspected
  • 5Appliances installed, connected, and tested
  • 6Punch list completed and signed off

Frequently Asked Questions

Ready to Use This Kitchen Remodel Template?

Fill in your project details and download a professional, customized scope of work PDF in seconds.