Project Overview
This scope covers elevator installation including shaft preparation coordination, equipment delivery, installation, wiring, testing, and inspection. Applies to passenger, freight, and residential elevators.
Typical Projects Include:
- New construction passenger elevator
- Residential home elevator installation
- Freight elevator installation
- Elevator modernization or replacement
- Limited use / limited application (LULA) elevator
- Dumbwaiter installation
Scope of Work
Pre-Installation
| Task | Description |
|---|---|
| Shaft & Pit Verification | Verify shaft dimensions, pit depth, overhead clearance, and machine room (if applicable) are built to spec. |
| Electrical Coordination | Confirm dedicated power supply, lighting, and phone line are in place per elevator requirements. |
| Equipment Delivery | Coordinate delivery of elevator car, rails, motor, controller, and all components to the job site. |
Installation
| Task | Description |
|---|---|
| Guide Rails & Brackets | Install guide rails, brackets, and buffers in the shaft. |
| Car & Counterweight | Assemble and install the elevator car, platform, doors, and counterweight system. |
| Motor & Controller | Install the drive motor, controller, and all associated wiring. |
| Door Equipment | Install hall doors, frames, sills, and door operators at each landing. |
Testing & Certification
| Task | Description |
|---|---|
| Adjustment & Testing | Adjust leveling, door timing, speeds, and safety devices. Test all functions. |
| Safety Testing | Test all safety systems including overspeed governor, safeties, buffers, and interlocks. |
| State Inspection | Schedule and pass the state elevator inspection to obtain operating certificate. |
Timeline & Milestones
Typical timeline for an elevator installation. Lead times on equipment can be significant.
| Phase | Duration | Description |
|---|---|---|
| Pre-Installation | 8-16 weeks | Equipment manufacturing, delivery, and shaft readiness verification. |
| Installation | 2-6 weeks | Rails, car, motor, controller, and door installation. |
| Testing & Certification | 1-3 weeks | Adjustment, safety testing, and state inspection. |
Roles & Responsibilities
General Contractor / Owner
- •Build shaft, pit, and machine room to elevator contractor's specifications
- •Provide dedicated electrical service and lighting in shaft and machine room
- •Provide phone line or emergency communication connection
- •Coordinate access and scheduling with elevator contractor
Elevator Contractor
- •Provide shaft layout drawings and requirements
- •Supply and install all elevator equipment
- •Complete all wiring within the shaft and machine room
- •Test all systems and coordinate state inspection
- •Provide maintenance agreement options
Materials & Equipment
Elevator Equipment
- •Elevator car and platform
- •Guide rails and brackets
- •Drive motor and controller
- •Counterweight (traction systems)
Doors & Fixtures
- •Hall doors, frames, and sills
- •Door operators and interlocks
- •Call buttons and position indicators
- •Car operating panel
Safety Equipment
- •Overspeed governor and safeties
- •Buffers
- •Emergency lighting and communication
- •Smoke detectors (if required)
Quality Control Standards
Code Compliance
Installation meets ASME A17.1 / CSA B44 Safety Code for Elevators and local requirements.
Manufacturer Standards
All equipment installed per manufacturer specifications and guidelines.
Safety Testing
All safety devices tested and certified before the elevator is placed in service.
Safety Protocols
Shaft Safety
Barricade shaft openings at all times when doors are not installed. Use fall protection inside the shaft.
Lockout/Tagout
De-energize all power before working on electrical components.
Rigging Safety
Use certified rigging equipment when lifting heavy components. Clear the area below during hoisting.
Project Documentation
- Signed contract and scope of work
- Shaft layout drawings and specifications
- Equipment submittals and approvals
- Permit and inspection records
- State operating certificate
- Maintenance agreement
Financial Terms
Payment Structure
Payments tied to manufacturing and installation milestones due to long equipment lead times.
Terms & Conditions
- •Deposit due at contract signing (typically 30-40%)
- •Progress payment due when equipment ships
- •Progress payment at installation midpoint
- •Final payment due after state inspection and certificate
- •Change orders require written approval
Acceptance Criteria & Sign-Off
The project is considered complete when the following criteria are met:
- 1Elevator operates smoothly at all landings
- 2All doors open, close, and interlock correctly
- 3Safety devices tested and functional
- 4State inspection passed and operating certificate issued
- 5Client trained on emergency procedures
- 6Maintenance agreement discussed and offered
Frequently Asked Questions
Ready to Use This Elevator Installation Template?
Fill in your project details and download a professional, customized scope of work PDF in seconds.
Related Templates
Electrical
Electrical Scope of Work Template
View Template →General Contractor
General Contractor Scope of Work Template
View Template →Concrete
Concrete Scope of Work Template
View Template →Steel Erection
Steel Erection Scope of Work Template
View Template →Framing
Framing Scope of Work Template
View Template →Drywall
Drywall Scope of Work Template
View Template →