Project Overview
This scope covers demolition work including selective interior demolition, structural teardown, hazardous material coordination, debris removal, and site cleanup.
Typical Projects Include:
- Interior selective demolition for remodel
- Full building demolition
- Kitchen or bathroom gut demo
- Commercial tenant space demo
- Concrete or asphalt removal
- Pool or deck demolition
Scope of Work
Planning & Prep
| Task | Description |
|---|---|
| Site Assessment | Walk the site to identify what's being removed, what's staying, and any potential hazards. |
| Utility Disconnect | Coordinate disconnection of electrical, plumbing, gas, and HVAC before demo begins. |
| Permits | Pull required demolition permits and schedule inspections. |
| Protection | Protect finishes, surfaces, and areas that are NOT being demolished. |
Demolition
| Task | Description |
|---|---|
| Selective Demo | Remove specified walls, ceilings, flooring, fixtures, and finishes as defined in scope. |
| Structural Demo | Remove structural elements as specified — walls, framing, concrete, etc. |
| Debris Handling | Load debris into dumpsters or trucks. Sort recyclable materials if required. |
Cleanup & Closeout
| Task | Description |
|---|---|
| Site Cleanup | Sweep, vacuum, and remove all debris from the work area. Leave the space broom clean. |
| Dumpster Removal | Arrange haul-off of all dumpsters and debris containers. |
| Final Walkthrough | Walk the site with the client or GC to confirm all demo work is complete. |
Timeline & Milestones
Demo timelines vary widely based on scope. Interior demo is fast; full building teardown takes longer.
| Phase | Duration | Description |
|---|---|---|
| Prep & Permits | 1-5 days | Utility disconnects, permits, and protection setup. |
| Demolition | 1-10 days | Demo work and debris loading. Duration depends on scope. |
| Cleanup | 1-2 days | Final cleanup and dumpster removal. |
Roles & Responsibilities
Client / General Contractor
- •Clearly define what is and isn't being demolished
- •Coordinate utility disconnections
- •Provide site access and dumpster placement area
- •Process payments per the agreed schedule
Demolition Contractor
- •Pull demo permits
- •Protect areas not being demolished
- •Perform all demolition work safely
- •Handle debris removal and disposal
- •Leave the site broom clean
Materials & Equipment
Protection
- •Plastic sheeting and dust barriers
- •Floor protection (ram board or similar)
- •Caution tape and signage
Tools
- •Reciprocating saws and demo hammers
- •Pry bars and hand tools
- •Skid steer or mini excavator (for larger jobs)
Disposal
- •Dumpster or roll-off container
- •Debris bags
- •Dump fees and hauling
Quality Control Standards
Scope Accuracy
Only specified items are removed — nothing extra gets demolished.
Clean Cuts
Demo lines are clean and straight where new work will tie in.
Protection Integrity
Protected areas remain undamaged throughout the demo process.
Safety Protocols
Hazmat Awareness
Test for asbestos and lead paint before demolishing older buildings. Use licensed abatement if present.
Structural Safety
Shore or brace adjacent structures when removing load-bearing elements.
Dust Control
Use dust barriers and wet methods to control dust. Wear respirators as needed.
PPE
Hard hats, safety glasses, gloves, and steel-toe boots required at all times.
Project Documentation
- Signed contract and scope of work
- Demolition permit
- Hazmat test results (if applicable)
- Utility disconnect confirmations
- Dumpster weight tickets
- Completion photos
Financial Terms
Payment Structure
Demo is often a short-duration job. Payment may be split between deposit and completion.
Terms & Conditions
- •Deposit due at contract signing (typically 30-50%)
- •Final payment due after demo and cleanup are complete
- •Dumpster and disposal fees may be billed separately
- •Change orders for unexpected conditions (hidden walls, hazmat, etc.)
- •Payment due within 30 days of invoice
Acceptance Criteria & Sign-Off
The project is considered complete when the following criteria are met:
- 1All specified items demolished and removed
- 2Protected areas undamaged
- 3Site is broom clean
- 4All debris hauled off
- 5Permits closed out
- 6Client walkthrough completed
Frequently Asked Questions
Ready to Use This Demolition Template?
Fill in your project details and download a professional, customized scope of work PDF in seconds.
Related Templates
Asbestos Abatement
Asbestos Abatement Scope of Work Template
View Template →Excavation
Excavation Scope of Work Template
View Template →Framing
Framing Scope of Work Template
View Template →Concrete
Concrete Scope of Work Template
View Template →General Contractor
General Contractor Scope of Work Template
View Template →Mold Remediation
Mold Remediation Scope of Work Template
View Template →